New Construction Project of Supreme Court Building Complex

Project Manager

Name: Manish Subedi

Project Status

Physical
0%
01/04/2021 15/12/2024
Financial
0%
01/04/2021 15/12/2024

Complete

2023-08-07
Uploaded Date: 2023-08-07
Uploaded Date: 2023-08-07
Uploaded Date: 2023-08-07
Uploaded Date: 2023-08-07
Uploaded Date: 2023-08-07
Uploaded Date: 2023-08-07
Uploaded Date: 2023-08-07

Project Detail:

New Construction Project of Supreme Court Building Complex
New Construction Project of Supreme Court Building Complex
Supreme court of Nepal
01/NCB/SC/077/078
Ramshah path,Kathmandu
01/04/2021
3 years
5,198,632,577.33

Progress Pictures