2023-09-17
Uploaded Date: 2023-09-17
Uploaded Date: 2023-09-17
Uploaded Date: 2023-09-17
Uploaded Date: 2023-09-17
Uploaded Date: 2023-09-17
Uploaded Date: 2023-09-17
Uploaded Date: 2023-09-17

Construction of Finishing Work for Academic Building (Block 3 Block 4 and Block 5) of St. Xavier’s School, Godavari

2022-05-23
Uploaded Date: 2022-05-23
Uploaded Date: 2022-05-23
Uploaded Date: 2022-05-23
Uploaded Date: 2022-05-23
Uploaded Date: 2022-05-23
Uploaded Date: 2022-05-23
Uploaded Date: 2022-05-23

Project Manager

Name: Mahesh Bhatta

Cell: 9851275795

E-mail: mhsbhatta@gmail.com

Project Status

Physical
0%
05/10/2018 02/06/2019
Financial
0%
05/10/2018 02/06/2019

Complete

2021-12-27
Uploaded Date: 2021-12-27
Uploaded Date: 2021-12-27
Uploaded Date: 2021-12-27
Uploaded Date: 2021-12-27
Uploaded Date: 2021-12-27
Uploaded Date: 2021-12-27

Project Detail:

Construction of Finishing Work for Academic Building (Block 3 Block 4 and Block 5) of St. Xavier’s School, Godavari
Construction of Finishing Work for Academic Building (Block 3 Block 4 and Block 5) of St. Xavier’s School, Godavari
ST. Xavier’s School, Godavari, Lalitpur
SXG/God/Oct/2018-3
Godavari
05/10/2018
05/10/2018
46,995,504.14